15.3. Parallel Plans
Because each worker executes the parallel portion of the plan to completion, it is not possible to simply take an ordinary query plan and run it using multiple workers. Each worker would produce a full copy of the output result set, so the query would not run any faster than normal but would produce incorrect results. Instead, the parallel portion of the plan must be what is known internally to the query optimizer as a partial plan ; that is, it must be constructed so that each process which executes the plan will generate only a subset of the output rows in such a way that each required output row is guaranteed to be generated by exactly one of the cooperating processes. Generally, this means that the scan on the driving table of the query must be a parallel-aware scan.
15.3.1. Parallel Scans
The following types of parallel-aware table scans are currently supported.
-
In a parallel sequential scan , the table's blocks will be divided among the cooperating processes. Blocks are handed out one at a time, so that access to the table remains sequential.
-
In a parallel bitmap heap scan , one process is chosen as the leader. That process performs a scan of one or more indexes and builds a bitmap indicating which table blocks need to be visited. These blocks are then divided among the cooperating processes as in a parallel sequential scan. In other words, the heap scan is performed in parallel, but the underlying index scan is not.
-
In a parallel index scan or parallel index-only scan , the cooperating processes take turns reading data from the index. Currently, parallel index scans are supported only for btree indexes. Each process will claim a single index block and will scan and return all tuples referenced by that block; other processes can at the same time be returning tuples from a different index block. The results of a parallel btree scan are returned in sorted order within each worker process.
Other scan types, such as scans of non-btree indexes, may support parallel scans in the future.
15.3.2. Parallel Joins
Just as in a non-parallel plan, the driving table may be joined to one or more other tables using a nested loop, hash join, or merge join. The inner side of the join may be any kind of non-parallel plan that is otherwise supported by the planner provided that it is safe to run within a parallel worker. For example, if a nested loop join is chosen, the inner plan may be an index scan which looks up a value taken from the outer side of the join.
Each worker will execute the inner side of the join in full. This is typically not a problem for nested loops, but may be inefficient for cases involving hash or merge joins. For example, for a hash join, this restriction means that an identical hash table is built in each worker process, which works fine for joins against small tables but may not be efficient when the inner table is large. For a merge join, it might mean that each worker performs a separate sort of the inner relation, which could be slow. Of course, in cases where a parallel plan of this type would be inefficient, the query planner will normally choose some other plan (possibly one which does not use parallelism) instead.
15.3.3. Parallel Aggregation
PostgreSQL
supports parallel aggregation by aggregating in
two stages. First, each process participating in the parallel portion of
the query performs an aggregation step, producing a partial result for
each group of which that process is aware. This is reflected in the plan
as a
Partial Aggregate
node. Second, the partial results are
transferred to the leader via
Gather
or
Gather
Merge
. Finally, the leader re-aggregates the results across all
workers in order to produce the final result. This is reflected in the
plan as a
Finalize Aggregate
node.
Because the
Finalize Aggregate
node runs on the leader
process, queries which produce a relatively large number of groups in
comparison to the number of input rows will appear less favorable to the
query planner. For example, in the worst-case scenario the number of
groups seen by the
Finalize Aggregate
node could be as many as
the number of input rows which were seen by all worker processes in the
Partial Aggregate
stage. For such cases, there is clearly
going to be no performance benefit to using parallel aggregation. The
query planner takes this into account during the planning process and is
unlikely to choose parallel aggregate in this scenario.
Parallel aggregation is not supported in all situations. Each aggregate
must be
safe
for parallelism and must
have a combine function. If the aggregate has a transition state of type
internal
, it must have serialization and deserialization
functions. See
CREATE AGGREGATE
for more details.
Parallel aggregation is not supported if any aggregate function call
contains
DISTINCT
or
ORDER BY
clause and is also
not supported for ordered set aggregates or when the query involves
GROUPING SETS
. It can only be used when all joins involved in
the query are also part of the parallel portion of the plan.
15.3.4. Parallel Plan Tips
If a query that is expected to do so does not produce a parallel plan, you can try reducing parallel_setup_cost or parallel_tuple_cost . Of course, this plan may turn out to be slower than the serial plan which the planner preferred, but this will not always be the case. If you don't get a parallel plan even with very small values of these settings (e.g. after setting them both to zero), there may be some reason why the query planner is unable to generate a parallel plan for your query. See Section 15.2 and Section 15.4 for information on why this may be the case.
When executing a parallel plan, you can use
EXPLAIN (ANALYZE,
VERBOSE)
to display per-worker statistics for each plan node.
This may be useful in determining whether the work is being evenly
distributed between all plan nodes and more generally in understanding the
performance characteristics of the plan.